15th February 2013- This was the date we started to plan all our work on what we will be doing a documentary on. Everyone in the group had their say and we took it in concern and came up with a plan of doing a documentary on stereotype and added a bit of everyone individual idea in.
21st February 2013- By this week we started to plan all the questions that we will be asking each person we interview. we came up with different sets of questions that are relevant to stereotyping and we asked what they think of it.
22nd February 2013- We started filming most the scenes by this date and got a few interviews done.
26th/28th February 2013 - We had a few people let us down and we won't able to interview them so we had to come up with a back up plan as soon as possible.
29th February 2013 - We managed to get the filming done and only had to start to edit and make sure everything was uploaded in our blogger.
5th March 2013 - We carried on filming the scenes we needed.
11th March 2013 - Filming and and planning to film new people.
20th March 2013 - We still was filming and editing the clips we already had.
1st April 2013 - We was on track and up to date most the scene were done just need to finish editing and do any extra work if needed.
8th April 2013 - By this date we had completed our Factual programming unit. All left to do was make sure everything is up to date and nothing was lacking on the blogger or on our video.